HP/SB-111
Workshop distribution board 111
Act before the equipment is next relied upon
Findings (4)
An unused way or cutout is open, so the enclosure no longer provides its rated protection.
Action Fit correct blanks and gland plates. Do not use tape or sheet offcuts.
Arc flash / electric shock · due 2024-01-04 · IEC 61439-1 §8.4.2
Cable terminations carry mechanical load that the connection was not designed to take.
Action Fit cleats or a support rail so no weight or pull is carried by the termination.
Arc flash / electric shock · due 2024-01-27 · AS/NZS 3000 §3.7.2
No thermographic survey has been recorded within the interval.
Action Book the survey while the board is under representative load, and file the report against the board identifier.
Loss of design or inspection traceability · due 2024-02-26 · NETA MTS §9.15
The circuit schedule does not match the installed ways, so isolation cannot be planned from it.
Action Verify every way and reprint the schedule inside the door.
Loss of design or inspection traceability · due 2024-01-27 · AS/NZS 3000 §2.10