NG/SB-104
Open assessment
Kestrel Process Group
Asset Integrity — equipment safety assessment

NG/SB-104

Packing hall sub-board 104

Report A-1027
Methodology v4.0
2025-12-28
Assessed risk
Moderate
Highest score
9
Findings
2
Immediate
0
Coverage
15/15
Next due
2026-12-28

Plan corrective work into the maintenance cycle

Asset class
LV switchboard / distribution board
Facility
Northgate Works, Ardmore Industrial Estate
Area
Utilities yard
Criticality
B
Manufacturer
Cortec Systems
Model / serial
M915 / 94376-74
Installed
2017-02-01
Inspector
M. Osei

Findings (2)

R-SB-13Enclosure damage affects ingress protectionNon-conformingS3 × L3 = 9Moderate

Physical damage has compromised the enclosure's rated ingress protection.

Action Repair the enclosure to its rating, and add protection if the damage was caused by vehicle or plant movement.

Arc flash / electric shock · due 2026-01-27 · IEC 61439-1 §8.2

R-SB-06Thermographic survey overdueRecords / traceabilityS2 × L4 = 8Moderate

No thermographic survey has been recorded within the interval.

Action Book the survey while the board is under representative load, and file the report against the board identifier.

Loss of design or inspection traceability · due 2026-02-26 · NETA MTS §9.15

Assessment record

Identification and records · Board identifierNG-SB-104
Identification and records · Is a current single-line diagram available at the board?Yes
Identification and records · Is the circuit schedule present and matching the installed ways?Yes
Identification and records · Is an arc-flash / shock-hazard label fitted?Yes
Enclosure integrity · Do the doors close and lock as designed?Yes
Enclosure integrity · Are all unused ways blanked and gland plates complete?Yes
Enclosure integrity · Are any energised parts reachable without a tool?No
Enclosure integrity · Enclosure damageAffects ingress protection
Terminations and thermal condition · Months since last thermographic survey31 months
Terminations and thermal condition · Was a hotspot recorded above the alarm threshold?No
Terminations and thermal condition · Are cable terminations supported and strain-relieved?Yes
Protection and access · Months since residual current devices were tested2 months
Protection and access · Is the main switch identified and its function labelled?Yes
Protection and access · Clear working space in front of the board1010 mm
Protection and access · Is the working space free of stored material?Yes

The PDF is generated server-side from this same data — same findings, same wording, same methodology version, plus the photo plate and a sign-off block.