Plantsight
← Equipment register
Northgate Works · Utilities yard

Packing hall sub-board 104

LV switchboard / distribution board · reassessed every 12 months · criticality B

Latest report
Current risk
Moderate
Plan corrective work into the maintenance cycle
Open findings
2
highest score 9
Last assessed
2025-12-28
by M. Osei
Next due
2026-12-28
On schedule

Findings on the current assessment

from A-1027 · methodology v4.0
Enclosure damage affects ingress protectionR-SB-13Non-conformingS3 × L3 = 9

Physical damage has compromised the enclosure's rated ingress protection.

Action Repair the enclosure to its rating, and add protection if the damage was caused by vehicle or plant movement.

Arc flash / electric shock · due 2026-01-27 · IEC 61439-1 §8.2

Thermographic survey overdueR-SB-06Records / traceabilityS2 × L4 = 8

No thermographic survey has been recorded within the interval.

Action Book the survey while the board is under representative load, and file the report against the board identifier.

Loss of design or inspection traceability · due 2026-02-26 · NETA MTS §9.15

Assessment history

2025-12-28 · M. Osei
A-1027 · assessed under v4.0
2 findingsModerateReport
2024-12-28 · T. Fenwick
A-1026 · assessed under v3.9
0 findingsLowReport

Historical assessments keep the methodology version they were completed under. Re-scoring old records against a newer version is an explicit action, never a side effect of publishing.

Asset record

Tag
NG/SB-104
Asset id
SB-104
Class
LV switchboard / distribution board
Manufacturer
Cortec Systems
Model
M915
Serial
94376-74
Installed
2017-02-01
Facility
Northgate Works, Ardmore Industrial Estate
Area
Utilities yard
Facility manager
H. Vance
Criticality
B

What this class is assessed on

  • Identification and records
    4 questions · photo + image analysis
  • Enclosure integrity
    4 questions · photo + image analysis
  • Terminations and thermal condition
    4 questions
  • Protection and access
    4 questions

15 active rules · 7 vision cues.