NG/SB-101
Compressor house distribution board 101
Stop use, isolate, escalate to the responsible engineer
Findings (4)
Temperature rise at a termination is far beyond the alarm threshold and failure is imminent.
Action Shed load from the affected circuit now and remake the termination before the board is reloaded.
Arc flash / electric shock · due 2026-06-28 · NETA MTS §9.15
An unused way or cutout is open, so the enclosure no longer provides its rated protection.
Action Fit correct blanks and gland plates. Do not use tape or sheet offcuts.
Arc flash / electric shock · due 2026-07-05 · IEC 61439-1 §8.4.2
The enclosure cannot be closed and locked, so access is not restricted to authorised workers.
Action Repair or replace the door hardware and re-key the board to the electrical suite.
Arc flash / electric shock · due 2026-07-12 · AS/NZS 3000 §2.9.2
No thermographic survey has been recorded within the interval.
Action Book the survey while the board is under representative load, and file the report against the board identifier.
Loss of design or inspection traceability · due 2026-08-27 · NETA MTS §9.15
Assessment record
The PDF is generated server-side from this same data — same findings, same wording, same methodology version, plus the photo plate and a sign-off block.