Plantsight
← Equipment register
Northgate Works · Goods in

Hydro-pneumatic accumulator 101

Pressure vessel / air receiver · reassessed every 12 months · criticality B

Latest report
Current risk
Moderate
Plan corrective work into the maintenance cycle
Open findings
1
highest score 6
Last assessed
2026-06-28
by M. Osei
Next due
2027-06-28
On schedule

Findings on the current assessment

from A-1002 · methodology v4.2
Working space around the vessel restrictedR-PV-15Improvement opportunityS2 × L3 = 6

There is not enough clear space to inspect, isolate or escape from the vessel position.

Action Clear and mark the working space around the vessel.

Access, egress and emergency response impaired · due 2026-08-27 · ISO 12100 §6.2.7

Assessment history

2026-06-28 · M. Osei
A-1002 · assessed under v4.2
1 findingModerateReport
2025-06-28 · R. Aldridge
A-1001 · assessed under v4.0
2 findingsModerateReport

Historical assessments keep the methodology version they were completed under. Re-scoring old records against a newer version is an explicit action, never a side effect of publishing.

Asset record

Tag
NG/PV-101
Asset id
PV-101
Class
Pressure vessel / air receiver
Manufacturer
Wessex Vessels
Model
V624
Serial
81961-48
Installed
2006-01-01
Facility
Northgate Works, Ardmore Industrial Estate
Area
Goods in
Facility manager
H. Vance
Criticality
B

What this class is assessed on

  • Identification and records
    5 questions · photo + image analysis
  • Pressure relief
    5 questions · photo + image analysis
  • External condition
    4 questions · photo + image analysis
  • Instrumentation and surrounds
    4 questions

16 active rules · 9 vision cues.