Case erector 102
Guarded machinery / conveyor · reassessed every 12 months · criticality A
Findings on the current assessment
from A-1056 · methodology v3.9An operator cannot reach an emergency stop from every working position.
Action Add stops or a pull-cord run so no working position is more than the methodology's distance from one.
Entanglement or crushing at moving parts · due 2025-06-11 · AS 4024.1601 §5.5
Stored energy is not documented, so isolation cannot be verified as complete.
Action Walk the machine with the maintainer, list every energy source, and publish it at the isolation point.
Loss of design or inspection traceability · due 2025-06-27 · ISO 14118 §6
Assessment history
Historical assessments keep the methodology version they were completed under. Re-scoring old records against a newer version is an explicit action, never a side effect of publishing.
Asset record
- Tag
- HP/GM-102
- Asset id
- GM-102
- Class
- Guarded machinery / conveyor
- Manufacturer
- Lindmark
- Model
- V946
- Serial
- 44948-26
- Installed
- 2007-03-01
- Facility
- Havenport Terminal, Dock Road
- Area
- Packing hall
- Facility manager
- S. Ilori
- Criticality
- A
What this class is assessed on
- Identification and records3 questions · photo + image analysis
- Guarding5 questions · photo + image analysis
- Emergency stop and isolation5 questions
- Workplace3 questions
17 active rules · 8 vision cues.