Goods-in gantry hoist 108
Overhead travelling crane / hoist · reassessed every 6 months · criticality C
Findings on the current assessment
from A-1055 · methodology v4.2The upper travel limit does not operate on test, so the block can be two-blocked into the crab.
Action Repair and prove the limit switch before the next lift.
Dropped or swinging load · due 2026-04-29 · AS 2550.1 §8.4
The rated capacity cannot be read from the equipment, so an operator cannot verify a lift is within limits.
Action Remark the SWL on the hook block and bridge in durable lettering visible from the operating position.
Loss of design or inspection traceability · due 2026-05-12 · AS 1418.1 §5.2
Assessment history
Historical assessments keep the methodology version they were completed under. Re-scoring old records against a newer version is an explicit action, never a side effect of publishing.
Asset record
- Tag
- HP/CR-108
- Asset id
- CR-108
- Class
- Overhead travelling crane / hoist
- Manufacturer
- Steelbridge Lifting
- Model
- B240
- Serial
- 97071-80
- Installed
- 2014-04-01
- Facility
- Havenport Terminal, Dock Road
- Area
- Boiler house
- Facility manager
- S. Ilori
- Criticality
- C
What this class is assessed on
- Identification and records4 questions · photo + image analysis
- Hook and block4 questions · photo + image analysis
- Rope, chain and reeving4 questions · photo + image analysis
- Controls, limits and structure5 questions
17 active rules · 9 vision cues.